Re: (Attock VU Group) PLZ MCS walo mughy CS605 ki Assignment k in steps ky just Answer bata dain ..thank u.

siso see this


Budgeted Cost of Work Schedule (BCWS) = Total BCWS=106

Budgeted Cost of Work Perform (BCWP) = Total BCWP=41

Budget at Completion (BAC)                         = Total BAC    = 415

Actual Cost Work Performed (ACWP)       = Total ACWP=43

 

 

 

 

1).        SPI (Schedule performance index)

 

SPI = BCWP/BCWS = 41/106 = 0.38

 

2).        Schedule variance (SV)

 

            SV = BCWP – BCWS = 41-106 = -65

 

3).        Percent scheduled for completion

 

            PSC = BCWS/BAC = 106/415 = 0.25

 

4).        Percent complete

 

            P C= BCWP/BAC = 41/415 = 0.098

 

5).        CPI

           

      Cost performance index CPI = BCWP/ACWP = 41/43 = 0.95

 

6).        Cost variance for the project.

      Cost variance CV = BCWP – ACWP = 41-43 = -2

 

 

--
██████████████████ Basic Group Rules ███████████████████
Immoral & Rudish talk, Earning program links, Cell number for friendship purpose, Websites/Groups Links, Adult contents, Criticize-able Islamic stuff, Spreading disruption, Spamming are strictly prohibited and banned in group.
█████████████████████████████████████████████████
 
Follow these detailed Group Rules, otherwise you will be banned at any time.
https://docs.google.com/document/d/1YJxA8x3_U7C1lRc0EXfLrJpco4A1XkB1vDxOTqOd3Jg/edit?hl=en&authkey=CNDy9tkJ
 
Group Email Address:
Attock-VU-Group@Googlegroups.Com
 
Join group by sending a blank email from University ID at:
Attock-VU-Group+Subscribe@Googlegroups.Com
 
Join us at http://www.Vusr.net for Papers,Assignments,GDBs, Quizes.
 
████████████ Click here to Join this group at Facebook:████████████
♥ ♥ ♥ https://www.facebook.com/home.php?sk=group_111877855568034 ♥ ♥ ♥
█████████████████████████████████████████████████

No comments:

Post a Comment