Budgeted Cost of Work Schedule (BCWS) = Total BCWS=106
Budgeted Cost of Work Perform (BCWP) = Total BCWP=41
Budget at Completion (BAC) = Total BAC = 415
Actual Cost Work Performed (ACWP) = Total ACWP=43
1). SPI (Schedule performance index)
SPI = BCWP/BCWS = 41/106 = 0.38
2). Schedule variance (SV)
SV = BCWP – BCWS = 41-106 = -65
3). Percent scheduled for completion
PSC = BCWS/BAC = 106/415 = 0.25
4). Percent complete
P C= BCWP/BAC = 41/415 = 0.098
5). CPI
Cost performance index CPI = BCWP/ACWP = 41/43 = 0.95
6). Cost variance for the project.
Cost variance CV = BCWP – ACWP = 41-43 = -2
--
██████████████████ Basic Group Rules ███████████████████
Immoral & Rudish talk, Earning program links, Cell number for friendship purpose, Websites/Groups Links, Adult contents, Criticize-able Islamic stuff, Spreading disruption, Spamming are strictly prohibited and banned in group.
█████████████████████████████████████████████████
Follow these detailed Group Rules, otherwise you will be banned at any time.
https://docs.google.com/document/d/1YJxA8x3_U7C1lRc0EXfLrJpco4A1XkB1vDxOTqOd3Jg/edit?hl=en&authkey=CNDy9tkJ
Group Email Address:
Attock-VU-Group@Googlegroups.Com
Join group by sending a blank email from University ID at:
Attock-VU-Group+Subscribe@Googlegroups.Com
Join us at http://www.Vusr.net for Papers,Assignments,GDBs, Quizes.
████████████ Click here to Join this group at Facebook:████████████
♥ ♥ ♥ https://www.facebook.com/home.php?sk=group_111877855568034 ♥ ♥ ♥
█████████████████████████████████████████████████
No comments:
Post a Comment